P&A Application in Norway North Sea

Well Abandonment with Wel-lok™ STC

Statistics

Identification of problem

This well had previously been abandoned by circulating a cement balance plug through perforations in 4 ½” tubing into a 7” production casing. The well continued to build gas pressure at surface through the production tubing and casing.

Issues to overcome

Traditional methods of circulating cement balance plugs does not generate a gas tight seal. In order to continue with the abandonment of the well, the operator needed to ensure the well was free of pressure and gas in order to cut and pull the production tubing.

Application

The production tubing was perforated and a Wel-lok™ STC was set in the well to provide a gas tight seal in the tubing and casing.

Outcomes/Conclusion

An initial pressure test of 4,000 psi was performed, followed by a successful negative pressure test which resulted in no bubbles or gas pressure at surface. Further, this well underwent a 1-year monitoring period prior to resuming the well abandonment, resulting in no bubbles or gas pressure build up over this period.

About the application

The Wel-lok™ STC (Seal Through Casing) has been developed to achieve a gas tight V0 seal well annuli that cannot be achieved by traditional cement balance plugs. Run on electric line, this tool does not need surface pumping equipment to circulate the alloy in place. Due to its viscosity and density, once melted the liquid alloy will flow with gravity into the annulus. When it cools below its melting point it solidifies, expands and creates a gas tight seal across the entire wellbore. The entire process, from melting to solidification, takes place in minutes and the seal is ready to test within an hour.

Seal Through Casing - BiSN
Seal Through Casing - BiSN
Seal Through Casing - BiSN
Seal Through Casing - BiSN

How it works…

The Wel-lok™ STC (Seal Through Casing) has been developed to achieve a gas tight V0 seal well annuli that cannot be achieved by traditional cement balance plugs.

How it works…

Get in touch to find a permanent solution for your well

Businesses worldwide are benefitting from BiSN's well services in the field. Contact us today and embrace tomorrow's downhole well solution, today.

This is a required field
Please enter a valid email
This is a required field
There has been an error. Please try again.
There has been an error. Please try again.
This is a required field

Don’t miss out on the latest technical updates and advancements. Subscribe today.

Please enter a valid email address.

Our website uses analytics, marketing and preference cookies to both provide the most relevant experience for our users and to give us information about how our site is used. By clicking “Accept All”, you consent to the use of these cookies. However, you may visit "Cookie Settings" to provide a controlled consent.

Accept All Cookies