×

Case Studies

Successful Shut Off of Multi-Annuli Gas Migration for Permanent Abandonment in Offshore California

Plug and Abandonment with Wel-lok™ Seal Through Casing (STC) Tool

An offshore platform located in the Santa Clara field off the coast of California was being abandoned. The wells were experiencing pressure and gas bubbles in the C and D annuli behind the 9-5/8” and 13-3/8” casings.

The 9-5/8” was cemented in the 13-3/8” casing, and the 13-3/8” casing itself was cemented inside an 18-5/8” casing of its own. The customer needed a tool that could do two things effectively – be deployed through the 9-5/8” on drill pipe and set a plug that would shut off gas migration in both annuli for a permanent abandonment out of the 18-5/8”.

The customer had made three previous attempts at abandonment and was looking for a more cost-effective solution for successfully shutting off all gas migration in the annuli. We took an existing BiSN tool and redesigned its deployment method to accomplish the customer’s specific needs. BiSN’s Bismuth-based alloy plugs are non-porous and non-corrosive and they expand into the casing to create a gas-tight seal. In total, using a BiSN plug leads to millions of dollars of savings that operators traditionally need to spend on costly section milling.

The tools needed to be deployed through the 9-5/8” casing on drill pipe. In order to make a 5 ft plug in the pipe’s 18-5/8” annulus, a certain amount of BiSN alloy needs to be deployed. Traditionally, this would be done by casting it directly onto the outside of the heater itself.

But the tool’s design is limited by two factors. Firstly, the well’s restrictions (9-5/8” casing) meant that the tool’s diameter could not be any bigger than 8.00” to successfully drift and make it down to its setting depth.

Secondly, making a plug to seal all the way out to the 18-5” casing requires a certain amount of energy to melt the alloy. This also meant that the heater’s diameter could not be made smaller to accommodate the volume of alloy by casting it on the outside.

In other words, using the traditional approach was not possible without making the tool itself extremely long.

Due to the well’s location off the coast of California, this project also had a critically high environmental impact.

 

By redesigning the alloy deployment mechanism, we were able to deploy the alloy in the form of small beads, instead of trying to cast it onto the heater itself where there were diameter restrictions.

Using the BiSN Bottom Hole Assembly (BHA) which included the bare heater and the running tool, we designed a solution that was able to be deployed on drill pipe using a specially created ported sub on top.

Once the tool was at setting depth, BiSN alloy beads were introduced into the drill pipe from the surface via the ported sub, gathering around the heater inside the section milled 18-5/8” casing. The heater was then ignited, melting all the alloy beads to make the plug. Then, the heater was retrieved, creating a full cross-section gas-tight alloy seal, and completing permanent abandonment.

Our BiSN Wel-Lok™ STC tool has been specifically developed to create a permanent barrier for abandonment through multiple casings and annuli, either through perforations or section milled windows.

 

Unlike cement, which requires hundreds of feet, the BiSN tool creates a gas-tight seal in just a few feet. It can also be deployed on both wireline and drill pipe.

Solution
  • Successfully shut off gas migration in C and D annuli
  • Significantly reduced rig time with millions of dollars saved
  • Reduced environmental impact and carbon footprint
  • Saved time by reducing section mill window length from 120 ft to 20 ft
  • Replaced a 100 ft cement plug with a sustainable 5 ft BiSN plug
  • Implementing a sustainable seal not affected by H2S or CO2

 

This successful project provided the customer with a more dependable and reliable seal than traditional cement. On top of the time and cost savings, our molten alloy solutions eliminated the need for surface pumping equipment.
Permanent abandonment was achieved through maximum innovation and minimum time and cost for the supermajor operator in question.
Are you looking for a cost-effective and sustainable solution for your business? Contact our technical team today.