New Era for Well P&A as Largest Bismuth Plug Deployed

BiSN, the global leader in metal-to-metal downhole sealing solutions, has achieved a world first in conjunction with AkerBP and Altus Intervention, through the successful deployment of the largest-ever bismuth plug.

Following over a year of development, BiSN’s award-winning Wel-lok M2M technology – which can be utilised during well and rigless well abandonment – was deployed via E-line in collaboration with Altus Intervention in AkerBP’s Valhall A-30 well in the Norwegian North Sea.

The Wel-lok M2M technology aims to bring substantial savings to operators by eliminating rig costs and doing the work rigless.

Conducted as a field trial, the tool was set to evaluate the effectiveness of bismuth as a permanent seal for P&A operations in lieu of cement. With 3,500 kg of bismuth alloy, a gas tight surface seal was created inside 18 5/8” casing through a section milled window cut in the 13 3/8” casing, entering previously unchartered territory regarding weight, size and precise setting procedures.

BiSN chief executive officer, Paul Carragher, said: “This project is an important step towards the adoption of bismuth well sealant technology. Wel-lok M2M drastically reduces the rig time needed to complete well abandonments (P&A) through the use of thermite heaters to melt bismuth-based alloys.

“We are fundamentally changing the way downhole sealing is carried out, and through trials like this, we continue to break the mould of traditional methods, changing the way operators look at well abandonment.”

Speaking about the project, Martin Straume, P&A Engineering Manager at AkerBP told us: “AkerBP is proud to be in front of the development of Bismuth as a barrier element with respect to Plug and Abandonment. In addition, this installation is proving that there is great savings potential in performing rigless P&A.”

Cathrine Bjaarstad, President Norway & Denmark, Altus Intervention said: “This project clearly demonstrates Altus Intervention’s ability to deliver innovative solutions and assist operators in resolving downhole challenges, adding value to their operations whilst creating both cost and time-savings”.

 

Latest News from BiSN

Dive deeper into BiSN and learn more about our performance barrier technologies.

BiSN recently granted 100th patent for precision oil & gas technology

300 global deployments

In the energy world, you’ll read many stats. Here’s some more for you: 300. For BiSN, that number is the culmination of 12 years of hard work.

OWI Global Awards Winners

Using our patented BiSN Wel-lok™ technology, our team set a world record for the heaviest bismuth alloy plugs ever – providing a permanent, gas tight, non-permeable seal with a 3000+ year life expectancy – infield tested and delivered ahead of schedule for our customer.

Get in touch and find a
permanent solution for your well

Businesses worldwide are benefitting from BiSN's well services in the field. Contact us today and embrace tomorrow's downhole well solution, today.

This is a required field
This is a required field
Please enter a valid email
This is a required field
This is a required field

Don’t miss out on the latest technical updates and advancements. Subscribe today.

Please enter a valid email address.

Our website uses analytics, marketing and preference cookies to both provide the most relevant experience for our users and to give us information about how our site is used. By clicking “Accept All”, you consent to the use of these cookies. However, you may visit "Cookie Settings" to provide a controlled consent.

Accept All Cookies